Scope of Services in Integrated Statutory Approvals

For new Project …Following approvals/ clearances are necessary in the Pre-establishment stage CFE (consent for establishment) and Preoperative stage CFO (consent for operation), We can provide consultancy for complete statutory approvals and licenses in 3 phases as follows

PHASE 1 - To Start Construction Activities, Following Licenses Are Required

  CFE from Pollution control board

  Ground water study & Bore Approval from State Ground water department

  Factory plan approval from Factories Department

  FIRE NOC from FIRE Safety Department

  Plan approval from DTCP/HMDA/IALA Departments – depending on Location of plant

  Power Feasibility (HT) Certificate From PDCL of respective states

  Registration of principal employer's establishment under The Contract Labor (Regulation and Abolition) Act, 1970

  Registration of establishments under The Building and Other Construction Workers(Regulation of Employment and Conditions of Service) Act, 1996

  Registration of establishment of principal employer under the Inter State Migrant Workmen (RE&CS) Act, 1979- if using the Inter State Migrant workers

PHASE 2 – After Finalization of All Equipment’s and at the End of Erecting Activities, Following Licenses Are Required


  Provisional electrical drawings approval from CEIG for erection of electrical equipment’s (From chief electrical in spectator)

Note:for preparation of these details, all electrical and other equipment’s should be finalized and single line diagrams are prepared.

  NOC from collector for explosive license-If any Explosive material stored.

PHASE 3 – After Completion of Erection Activities and Before Starting the Production, Following Licenses Are Required As CFO (Consent For Operation) Or Occupancy Certificates


  CFO from Pollution control board

  Final Factory drawings approval from Factories Department ( by mentioning any deviations or additions and deletions happened compare to initial Factory drawings approved after site inspection by Deputy chief Inspector of factories)

  Occupancy Certificate from FIRE Safety Department (by mentioning any deviations or additions and deletions happened compare to initial Fire drawings approved)

  Factory License to run a factory from Inspector of factories

  Occupancy certificates / Approval from IALA /DTCP/HMDA

  Labor license (Registration for deployment of contractual workmen and any additions)

  Final CEIG inspection and Approval from chief electrical in spectator (by mentioning any deviations or additions and deletions happened compare to initial electrical drawings approved)